TSC – Transmission System Operator Security Cooperation top

Home  > Timeline

Timeline

1 October 2011
Signing of the Operational Agreement / Start Trial Phase on MRA

13 September 2011
Signing of the Agreement on multilateral remedial actions (MRA)

12 September 2011
TSC CEO Strategy Meeting (Switzerland)

8 August 2011
Start IDCF Introduction Phase

30 May 2011
TSC – NRA’s workshop (Austria)

25 May 2011
TSC CEO Meeting

3 January 2011
Operational start of CTDS System and Video Conferencing System

10 November 2010
TSC regulator workshop in Prague (Czech Republic)

19 October 2010
TSC CEO meeting in Amsterdam (The Netherlands)

September 2010
Two additional TSOs (ELES and HEP-TSO) to join the Transmission System Operator Security Cooperation

January 2010
Czech companies Unicorn Systems and ELEKTROSYSTEM win tender for TSC software platform for common security analyses

December 2009
Final awarding of vendors and start of CTDS-implementation

30 Oktober 2009
Signing of Financial Agreement

13 November 2009
TSC CEO Meeting in Zurich (Switzerland)

August 2009
Tendering procedure for European IT platform launched

July 2009
Launch of real-time security monitoring system for Central Europe

January 2009
  • Establishment of project structure and “TSO Security Panel”
  • Conclusion of project management contract
  • Agreement on project plan and deadlines

18 December 2008
Signature of agreement (11 TSOs, Mavir expresses interest to join soon)

 